Kirk Hill Monthly Blog Updates

February & March

All the physical works on the grid connection has now been completed by SP Energy Networks and their contractors, and their protection engineers are carrying out the final stage of the work to set up and test the communication links and safety equipment. Energisation is still forecasted for the end of April which will allow the turbines to be commissioned in May.

As energisation approaches, work has been non-stop. All 6km of the grid connection route is now fully installed, with protection and commissioning work for the connection now underway and on track.

In addition, electrical fit-out works in the substations have been completed, as well as all local road resurfacing. Things really are on the final stretch now.

Things are moving at pace ahead of the switch-on at Kirk Hill with reports confirming that all 70 poles for grid connection have now been installed. Alongside, 4km of 5km of overhead line conductors have been successfully installed on poles and the electrical fit-out works in both substations are nearing completion.

Work continuing at Kirk Hill wind farm site.

With the specialised fibre joint kits and cables now on site, SP Energy Networks have been making great progress on the grid connection. Energisation is still on track for the end of April, with the turbines due to be commissioned in May. Work is also underway resurfacing the public road near the site and reinstating verges on the access route.

Jamie has filmed one of his invaluable update videos for you all too and you can catch that here.

Progress at Kirk Hill continues to deliver results. Last month the 1km underground cabling portion of the grid connection was completed, plus low-voltage standby power supplies are now live in both substations, ready for commissioning control equipment.

Switch gear being offloaded at Ripple Energy's Kirk Hill wind farm site.

The site looks a little emptier too as all of Enercon’s tools, containers and cabins have been transported off-site.

Energisation is now programmed for April, and the subsequent commissioning in May. As we edge ever closer to these milestone moments, rest assured we will keep you regularly updated.

August  

What had been delivered so far?

  • Full set for Turbine 1
  • Full set for Turbine 2 
  • Full set for Turbine 7
  • Hubs, nacelles, generators for Turbine 3, 4, 5, 6 and 8

June and July

May

Close Menu

Discover more from Blog | Ripple Energy

Subscribe now to keep reading and get access to the full archive.

Continue reading